Reid Highway Interchanges

Altone Road and Drumpellier Drive/Daviot Road

Under constructionUnder Construction

Constructing new interchanges for a safe and continuous route for residents, tourists and heavy vehicles.

Aerial shot of Reid Highway interchanges

What's happening

Thank you to all community members that attended our night markets in October.

Designs for the new bridged interchanges at Altone Road and Drumpellier Drive/Daviot Road are well underway, and we’re inviting the community to join us to view the latest plans and speak to the team at our next community drop-in session.

When: Wednesday 3 December

Where: Caversham Community Centre,135 Suffolk Street, Caversham

Time: From 3pm to 6.30pm

If you’re unable to attend and would like to speak to a member of the project team, please email enquiries@mainroads.wa.gov.au or ring 138 138 (24 hours) for more information on the project.   

 Principal Shared Path (PSP) and local path detours

To allow construction activities to be completed safely and enable future traffic switches, we will need to divert pedestrians and cyclists away from the PSP along Reid Highway and at Altone Road and Drumpellier Drive / Daviot Road.

To minimise disruptions to PSP and path users, long-term diversions will be implemented and will be in place until the project is complete. Approved detour routes will guide pedestrians and cyclists through the local road and path network.

While some of the routes are anticipated to increase travel time, several options were assessed to minimise impacts while ensuring safe connectivity. Minor improvement works will also take place along the detour routes including additional fencing and signage to support safe travel.

The first closure is proposed for a section of PSP along Reid Highway between west of Altone Road and west of Arthur Street Bridge, along with the Drumpellier Drive PSP south of Marshall Road. These closures are anticipated from late-October and are required to enable construction works to proceed and to keep pedestrians and cyclists safely separated from active work zones.

Subsequently, the Grandis Road underpass is anticipated to close from mid-November, to allow for ramp construction and underpass extension works. In addition, the pedestrian crossing on Altone Road will be shifted to the eastern side of the road, with temporary pavement installed to maintain safe access.

Additional path closures may be required as works progress and we will continue to provide updates and advance notice of any further changes. Please note that the timeframes to implement the above closures are not final and are subject to change.

More information on the timing of the closures and detour maps will be provided soon.  

Temporary shared path closures

The following Principal Shared Path (PSP) and local path closures will be implemented from early December 2025:

  • Reid Highway PSP - west of Altone Road to Arthur Street Bridge
  • Drumpellier Drive PSP - south of Marshall Road
  • Grandis Road underpass - connecting Grandis Road and Reid Highway PSP

These temporary closures are necessary to ensure the safety of path users while major bridge and ramp works take place. The closures will remain in place until approximately July 2027, with updates on timing provided throughout the project.

Detour route
During the closure, pedestrians and cyclists will be detoured via the local path and road network.

Reid Highway Interchanges - Principal Shared Path Closure Detour Map
Click to enlarge

Future detours and temporary closures

As works progress, additional path closures and detours will be required to support bridge and ramp construction. Advance notice and updated maps will be provided to minimise disruption.

 New traffic conditions on Reid Highway

The speed limit on Reid Highway between Altone Road and Drumpellier Drive / Daviot Road has been temporarily reduced to 80 km/h for the duration of the project due to increased construction activity and presence of workers on site.  

We encourage all road users to adhere to the new speed limits and take caution while driving through changed traffic conditions in the area.

 What's coming up?

We have commenced vegetation clearing across the project, which will continue through to early December. Nearby residents and road users may notice an increase in truck movements and activity as works progress. We are closely monitoring work impacts.  For more information on our clearing works, view the Frequently Asked Questions.

Construction of our site facilities are well underway and we are expected to start to use the compound from late-October 2025. To minimise impacts on nearby residents, vehicle access into site will be from Drumpellier Drive only, and will operate on a left-in-left-out basis.

Read our November Construction Update.

 Are you interested in working on the project? Contact enquiries@mainroads.wa.gov.au to be connected with a project representative or click to express interest.

Greater

safety and flow

Improved

route for freight

Continuous

shared path for cyclists and pedestrians

Page last reviewed:  | Last updated: 

Acknowledgement of Country

The Government of Western Australia acknowledges the traditional custodians throughout Western Australia and their continuing connection to the land, waters and community. We pay our respects to all members of the Aboriginal communities and their cultures; and to Elders both past and present.

Tell us what you think

Help us improve our website by sharing your thoughts and suggestions.

Provide feedback